The Digging Deeper model methodology is based on the methodology used in A Green Iron Plan for Australia with updates to better reflect how a green iron facility would interact with WA’s Wholesale Electricity Market.

The model simulates the dynamic behaviour of a complete green iron production system over an example year.

The simulation is run multiple times to identify the investments and production levels that deliver the lowest levelised cost of iron (LCOI). Each run of the simulation uses different combinations of investments and production volumes.

Scatter plot of example data showing cost of iron against iron plant utilisation for many simulation runs
How the model simulates an iron production system

The simulation runs in hourly steps for a full year (8,760 hours).

Within each hour, the simulation estimates the energy required to meet iron-making needs. If the energy requirements can be met, then the iron-making system produces at full capacity in that hour.

If there is not enough energy available, the system will try to use stored energy (e.g., from electricity stored in a battery, or hydrogen). Electricity will also be drawn from the grid up to the limit imposed by connection constraints and the Hydrogen Production Tax Incentive (HPTI) carbon-intensity limit. If there is still not enough energy, other forms of production are constrained (e.g., water and hydrogen).

The model prioritises the supply of electricity to production processes in the following order:

  1. water processing (low energy use; a necessary input for all downstream processes);
  2. iron-making;
  3. hydrogen-making.

This approach ensures that the iron plant operates whenever hydrogen is available from simultaneous production or drawn from storage.

To capture the effect of a green iron facility importing electricity from the Wholesale Electricity Market (WEM), the forecast total WEM demand requirement is increased by the green iron facilities demand. The market clearing price is then calculated as the price offered by the facility which is the last one dispatched (dispatching in order from lowest price to highest). This is illustrated in Figure A.

In the previous model, the market price of electricity was taken as the historic clearing price. This did not account for the impact of the green iron facilities demand on the price, which will tend to increase it. The new approach incorporates this impact.

Chart of bids into the electricity market in order of price. Adding green iron facility demand to the base forecast demand raises the clearing price.

For the export case, the forecast total WEM demand requirement remains unaltered. However, the green iron facility now adds its target export volume to the supply in the bid stack. The new supply is offered in two separate bids. The first bid, of otherwise curtailed electricity, is offered at $0/ MWh. As long as the market clears above this value, this will generate additional revenue for the green iron system if dispatched.

The second bid is the quantity of electricity that is used to run the electrolysers. This is bid at an estimate of the ‘breakeven’ cost of electricity for the green iron system. This is the price of electricity at which it is more valuable to sell the electricity back to the market than to use it to produce green iron. This bid will only be dispatched if the clearing price is at or above the breakeven price. Figure B illustrates a bid stack where the first bid clears and is dispatched but the second bid does not.

Both bids will increase the volume of supply in the market, so will tend to drive clearing prices down, relative to the actual historic clearing price.

Chart of bids into the electricity market in order of price. The green iron system’s $0 bid is below the new clearing price and is dispatched; its breakeven-price bid is above it and is not.

To approximate the Reserve Capacity Mechanism (RCM) in our model, we have included a new flag in the input hourly historic data which identifies if an hour was a peak period.

The model treats peak periods differently depending on whether the case is a flexible or inflexible case.

This means that for flexible cases, that are typically able to optimise around peak periods, grid interaction is prohibited during peak periods and no RCM cost is incurred. Neither does the facility generate revenue under the demand side response component of the RCM because we cannot guarantee that the iron production system will be drawing from the grid in any given hour.

For the inflexible cases, we conservatively assume that under the RCM the inflexible plant is classified as a Temperature Dependent Load. This implies slightly higher reserve capacity costs with regard to median consumption in the 12 peak periods.

The maximum demand over the peak periods is used to estimate the RCM liability.